Culvert Installation
Tender ID: 530458
Tender Details
Tender Description
The Shire of Kulin requires a suitable qualified contractor for the installation of culvert pipes in 3 locations for the upcoming financial year 2023/24, locations are as follows,
Fence Rd North from SLK 0.00 to 7.00,
Kulin Holt Rock Rd SLK 49.80 to 64.80,
Yealering Rd Corrigin Kulin Rd Intersection
Culvert Installation Requirements
Fence Rd Nth - Various Locations
11 full-length pipes 375mm x 12 metres,
Kulin Holt Rock Rd - Various Locations
8 full length pipes 375mm x 12 metres, with headwalls
1 full length pipe 450mm x 12 metres with headwalls
1 full length double pipe 375mm x 12 metres with headwalls
1 full length double pipe 450mm x 12 metres with headwalls
1 full length 3 barrel pipe 375mmx 12 metres with headwalls
1 full length 4 barrel pipe 450mm x 12 metres with headwalls
1 full length box culvert 600mm x 600mm x (2.4m) 12 metres with headwalls.
Yealering Rd Corrigin Rd Intersection
1 full-length box culvert 600mm x 300mm 2.4m with headwalls
1 pipe,1 x 300mm extension on both sides of existing pipe with headwalls
1 pipe 1 x 300mm extension on both sides of existing pipe with headwalls
3 pipes 2 x 375mm, 1 x 300mm extension on both sides of existing pipe with headwalls.
The Contractor will be required to undertake the following,
Install pipes in locations supplied by the Shire in various locations to replace existing pipes.
ALL pipes must be laid on a bed of aggregate. Aggregate supply be Shire.
All pipes must be backfilled with stabilised material supplied by the Shire.
Backfill must be to the level of the existing road level and must be set before opening to traffic.
Level and Screed stabilised back to cover the entire length of pipe to the headwall.
Install headwalls to each pipe supplied by Shire.
Patching of each headwall around the pipe to form a watertight seal.
Spoil must be removed and disposed of offsite in an area designated by the Shire.
Clear the inlet and outlet of each pipe to allow water to flow freely.
Additional Information
Traffic management is to be supplied by the Shire.
Shire to supply fuel
Shire to supply pipes and headwalls.
Pipes are 6m lengths and 375mm in diameter.
Headwalls are concrete.
Pipes are black corrugated from Enviropipes.
Pipe extension will be Class 4 concrete.
Contractor may choose to work in more than one location if Traffic Management permit.
Site Visit recommended.
Further details may be obtained from Judd Hobson via email: works@kulin.wa.gov.au