Tokomaru Stopbanks Upgrade - Phase 2
Tender ID: 568802
Tender Details
Tender Description
Preparation: The clearing and removal of all obstacles and vegetation as necessary within the Site, including borrow areas.
Stripping: The removal of topsoil from the area affected by the earthworks, including fill and borrow areas.
Excavation: The excavation of all cuts, borrow areas, benches and surface drainage facilities.
Carting: The carting of the excavated material to fill or to waste.
Filling, Reinforcement and Compaction: The placement of Type A fill into the stopbank and the shaping of stopbank batters.
Control of Surface Water: The control of surface water throughout the period of operations to prevent erosion of the landscape and the silting of waterways, and to protect the earthworks.
Spreading: The spreading of stockpiled vegetation on the berm and the spreading of topsoil and the sowing of grass.
Spraying: The spraying of polymer infused hydroseed where necessary.
Maintenance: Maintenance of the Contract Works.